Zagtouli post

Strategic cross-border interconnection

In 2017, as part of the project to interconnect the electricity grids of Burkina Faso and Ghana, These facilities are part of the ambitious project to interconnect Boltanga and Ouagadougou, entrusted to Eiffage Énergie Systèmes by Société nationale d'électricité du Burkina Faso (SONABEL) and the Ghana Grid Company (GRIDCo). 

Featuring two high-voltage transformer yards in Ouagadougou and 200 km of 225 kV power lines, this project is part of a larger cross-border development programme to share power transmission infrastructures in West African countries. 

Eiffage Énergie Systèmes successfully completed the works for the turnkey facilities.